Spain Renovation Permits in 2026: The Complete Guide to Licenses, Fines, and Legal Reforms
  • 15+Years renovating on the coast
  • 120+Homes & apartments delivered
  • < 48 hAverage quote time
  • 4.9/5Average client rating

Spain Renovation Permits in 2026: The Complete Guide to Licenses, Fines, and Legal Reforms

Renovating in Spain? Get the 2026 guide to building permits, licenses, fines, and new legal reforms—explained simply for your project.

29 September 2026

Spain Renovation Permits in 2026: The Complete Guide to Licenses, Fines, and Legal Reforms

Renovating a property in Spain in 2026 offers more promise—and more legal complexity—than ever. New municipal ordinances, streamlined digital permit portals, and stricter fine structures are reshaping how homeowners and investors approach even the smallest refurbishment. Whether you’re updating a bathroom in Barcelona, overhauling a structure in Madrid, or restoring a rural farmhouse in Andalusia, one licensing misstep can stall your project for months or cost thousands in penalties. This guide cuts through the bureaucracy. It explains which permits you need, how recent legal reforms affect your timeline and budget, and what the updated fine schedules mean for unlicensed work. By the end, you’ll have a clear roadmap to secure your licenses legally, avoid common pitfalls, and navigate Spain’s 2026 renovation rules with confidence.

Why Spain’s Permit System Matters in 2026

Spain’s renovation landscape is a layered puzzle. At the national level, the Ley de Ordenación de la Edificación (LOE) sets the baseline rules for construction quality, liability, and professional oversight. But the LOE does not grant permission to build; it only defines technical and safety standards. The real authority to approve or deny your project rests with each of Spain’s 17 autonomous communities, which operate under their own Ley de Ordenación del Territorio y Urbanismo. These regional laws can impose stricter setback requirements, protected heritage zones, or mandatory energy-efficiency upgrades that go well beyond national norms. In 2026, you cannot rely on the LOE alone—you must cross-reference it with your region’s urban planning code and, crucially, your local ayuntamiento’s municipal ordinance. Madrid, Barcelona, Valencia, and Seville each have distinct procedural timelines and documentation demands. Starting work without this three-tier check is the fastest route to a stop-work order.

What Counts as a “Renovation” That Requires a Permit

The line between “minor work” and “major renovation” is not intuitive. In 2026, any alteration that touches the structure, volume, exterior appearance, or legal use of a property triggers a full licencia de obras. That is non-negotiable. Still, the system does offer relief for purely cosmetic updates, though the exemption is rarely automatic.

  • Full permit required: Structural changes (moving or removing load-bearing walls), roof modifications, facade alterations, changing a room’s layout, adding new windows or doors, and changing the property’s use (e.g., from residential to tourist rental or commercial). These require a full licencia de obras and typically need a técnico competente (architect or technical architect) to sign off on a project.
  • Possibly exempt but with prior notice: Replacing non-structural flooring, repainting interior walls, installing new kitchen cabinets, or swapping bathroom fixtures. These may not require a full permit, but you will almost always need to file a comunicación previa or declaración responsable with your ayuntamiento. This is a formal declaration that your work complies with regulations, and you must submit it before any tool touches the wall.
  • Always check your local ayuntamiento’s ordinance: Exemptions vary wildly by city. Some municipalities have abolished the comunicación previa for interior painting; others require it even for changing a door handle. In 2026, the safest move is to spend €50 to €150 on a quick consultation with a local aparejador to confirm your project’s classification before you file anything.

Assuming you need a permit, processing fees range from €200 to €1,200 for small residential renovations, depending on the municipality and the project’s complexity. For larger structural work, professional fees for the compulsory proyecto técnico will add roughly €1,500 to €6,000, depending on the architect’s experience and the scope of your changes.

The Two Main Types of Permits: Licencia de Obras vs. Declaración Responsable

Before you touch a wall in Spain, the single most important decision is identifying which permit your renovation needs. Get it wrong, and you risk fines starting at €600 and climbing past €100,000 for serious structural violations—plus the cost of demolishing unapproved work at your own expense. The system isn’t as complicated as it sounds, but it does require you to classify your project correctly from the start.

Licencia de Obras: When You Must Get Explicit Approval

The licencia de obras is the classic, full building permit. It’s mandatory for any work that alters the structure, changes the exterior appearance, modifies the number of dwellings, or touches load-bearing walls, facades, roofs, or communal areas. The process is straightforward but slow. You commission a complete technical project from an architect or technical architect, who prepares detailed plans, structural calculations, and a health and safety study. This dossier goes to the town hall, where urbanism technicians review it against the municipal General Plan (Plan General de Ordenación Urbana) and local zoning rules. Approval is explicit—the town hall actively grants written permission before you can legally start. Expect the process to take one to three months. Professional fees for the technical project on an average apartment renovation run from €1,500 to €8,000, depending on complexity. The license itself carries municipal fees, typically 2% to 4% of the declared construction budget.

Declaración Responsable and Comunicación Previa: Faster, But Still Mandatory

For minor works that don’t alter the structure or exterior—replacing interior flooring, updating a kitchen, installing new plumbing, painting interior walls—many municipalities offer a faster route. You file a declaración responsable (a sworn statement that your work complies with all regulations) or a comunicación previa (a simple notification). The key advantage: you can start immediately after filing, with no waiting for approval. But speed comes with a serious catch. You’re certifying, under your own responsibility, that the work is legal. If your declaration is false, incomplete, or omits that you’re actually knocking down a structural wall, the town hall treats it as if you had no permit at all. Penalties are identical, and you lose any leniency that might have applied to someone who simply erred in a full license application.

“In 2026, the trend across Spanish municipalities is to expand the list of works requiring a declaración responsable, but never assume—always verify with your local town hall’s urbanism department before starting.”

Fees for a declaración responsable are nominal—often under €100—and you can file it yourself without hiring an architect for the paperwork. Still, you need a qualified professional to sign off on technical compliance for anything beyond cosmetic changes. Always confirm exact requirements with your town hall; some municipalities have their own forms and supplementary fees.

Step-by-Step: How to Apply for a Building Permit in 2026

Applying for a renovation permit in Spain is a structured process that rewards preparation. The ayuntamiento (town hall) is not your adversary—it is a compliance gatekeeper. Follow the sequence below, and you can avoid the most common delays and the fines that currently range from €600 to €6,000 for unlicensed work, depending on the municipality and the severity of the infraction.

Documents You Need Before You Apply

Assemble your dossier before you think about submitting anything. You will need a cadastral certificate identifying the property’s exact boundaries and use, a nota simple from the land registry proving legal ownership, and a copy of the community’s approval if your renovation touches shared elements like a facade, roof, or structural wall. The centerpiece is a full technical project—not a sketch—signed by a qualified architect. This document must include detailed plans, material specifications, and compliance with the CTE (Código Técnico de la Edificación). For larger works exceeding €100,000 in budget or involving structural changes, you will also need a waste management plan and a health and safety study prepared by a coordinator.

The Application Process at Your Local Ayuntamiento

Once your documents are ready, submit your application in person at the urbanism office or—in most large municipalities like Madrid, Barcelona, or Valencia—through their digital portal. The town hall will cross-check your project against zoning laws, building codes, and heritage protection rules. Expect possible requests for corrections; this is normal, not a rejection. The legal clock only starts ticking once your file is deemed complete. If everything is in order, the permit is typically granted within 2 to 4 months. If the town hall misses its deadline, you may fall under administrative silence (silencio administrativo)—but beware: in many regions, silence on major works is negative, meaning your application is denied by default, not approved.

To keep your timeline realistic, follow these steps in order:

  • Step 1: Gather ownership and cadastral documents.
  • Step 2: Hire an architect to draft the technical project (fees run from €1,500 to €8,000 for a standard apartment renovation).
  • Step 3: Obtain community approval if common elements are involved.
  • Step 4: Submit the full application to the ayuntamiento, paying the construction tax (ICIO), typically 2% to 4% of the project’s execution budget.
  • Step 5: Respond to any requests for additional information within the given deadline—usually 10 to 15 working days.
  • Step 6: Receive your permit in writing, or formally confirm whether administrative silence applies in your specific case.

How Long Does It Take? Deadlines and Administrative Silence

In 2026, the standard legal maximum for a municipal decision on a building permit is three months, though many municipalities have local ordinances that shorten this to one or two months. If your town hall doesn’t respond within the deadline, you must understand what silence means. This three-month ceiling applies to obra mayor—structural changes, extensions, or alterations affecting the building’s safety, stability, or occupancy. But don’t celebrate the timeline yet: the clock often stops if the council requests additional documentation, and each request can reset the countdown. Before you submit, check your local ordenanza municipal—cities like Madrid, Valencia, and Barcelona routinely operate on 30- to 45-day internal targets, while smaller towns may stretch the full 90 days. A practical tip: pay the application fee with a bank transfer that leaves a timestamp, and submit via the electronic registry (sede electrónica) to generate a legally binding receipt. Without that, you have no proof of when the clock started.

Silencio Administrativo: When No Answer Means “No” (or Rarely “Yes”)

For major works, administrative silence is negative—meaning your permit is denied by default. For minor works or declaraciones responsables, silence may be positive only if the law explicitly says so. Never assume silence means approval; always request a written confirmation or file an appeal if you receive no response. The distinction matters more than most homeowners realise: a negative silence after three months means you must restart the process from scratch, and any work already begun becomes illegal. Positive silence—where lack of response equals approval—applies only in narrow cases, such as certain obra menor (non-structural repairs, interior partitions, or facade maintenance under specific square-meter thresholds) and only if your local ordinance explicitly states that positive silence applies. In 2026, the trend is toward tightening this: many councils now require you to file a certificado de silencio positivo with the colegio de arquitectos before any work starts, and they routinely reject it if the application was incomplete.

“In practice, relying on positive administrative silence in 2026 is extremely risky. Most town halls will treat silence as a denial for structural works, and starting without a written permit exposes you to immediate stop-work orders.”

The safest course: after the deadline passes, file a formal escrito requesting a certified copy of the resolution. If none exists, lodge an recurso de alzada (appeal) within one month. This forces the council to issue a written decision—either approving retroactively or confirming the denial—and gives you legal standing for compensation claims if the delay causes financial damage. Budget for legal fees from €500 to €2,500 per appeal, depending on complexity and whether you hire an abogado.

Special Rules for Protected Buildings and Historic Districts

If your property is declared a Bien de Interés Cultural (BIC) or sits within a protected historic district, the standard municipal permit process is only half the battle. You will need a separate, additional authorization from the regional cultural heritage authority before the ayuntamiento can even consider your application. This heritage approval is a distinct legal gateway—not a formality—and it runs on a slower, more rigorous timeline. In 2026, the average wait for this combined review ranges from 6 to 9 months, so factor that into your project schedule before hiring contractors or ordering materials. If the complexity feels overwhelming, let us handle the permits for you and keep your project moving without the bureaucratic headaches.

Additional Documentation and Stricter Review

For protected buildings, your technical project must include a heritage impact assessment. This document goes far beyond a standard architectural plan; it must detail how every proposed change affects the building’s historical value, structural integrity, and visual relationship with its surroundings. The regional authority will scrutinize any modifications to facades, roofs, windows, or original materials—down to the type of mortar, paint color, and joinery profiles. In 2026, many regions have tightened these requirements, especially for energy efficiency upgrades. Replacing historic single-glazed windows with modern double glazing, for example, is frequently rejected unless you can prove the new units replicate the original sightlines and profiles. Similarly, adding interior insulation to exterior walls may be denied if it risks trapping moisture in original masonry.

Specifically, you should prepare for the following:

  • You must obtain heritage authorization before submitting to the ayuntamiento; submitting in reverse order will likely result in automatic rejection.
  • Works that alter original features—such as removing original floor tiles, plasterwork, or wooden beams—are often denied outright, not merely modified.
  • Some regions now require a specialized archaeologist or heritage architect to be part of the project team, adding from €2,500 to €6,000 to your professional fees.
  • Expect longer processing times—often 6 months or more—and budget for potential additional studies, such as a stratigraphic analysis of wall layers, which can cost from €800 to €2,200 per elevation.

The key takeaway: do not buy a property in a historic district expecting to make cosmetic changes quickly. Engage a local heritage consultant early, and treat the authorization as a project milestone in its own right, not a checkbox.

Homeowners’ Community Approval: A Step Many Forget

The 2021 Reform of the Ley de Propiedad Horizontal Still Applies

Own a flat or townhouse in a managed development? Your renovation doesn’t start at the town hall—it starts in the community meeting room. The 2021 reform of the Ley de Propiedad Horizontal (Spain’s Horizontal Property Law) remains fully in force in 2026, and it reshaped the approval workflow. Any work touching common elements—facades, roofs, structural walls, entrance areas, even shared utility risers—requires prior, documented approval from the comunidad de propietarios at an extraordinary meeting. This isn’t a courtesy; it’s a legal prerequisite. Crucially, you must secure this approval before submitting your municipal permit application. Many owners assume the municipal license is the only green light needed. In practice, the town hall often asks for proof of community approval on shared structures. Present your project to the community after work has started, and you’re already breaching civil law.

How to Get Community Approval and What Happens If You Don’t

The process is formal and time-sensitive. Request an extraordinary meeting from the president, supplying a written description of the works, a basic plan, and an estimate of their impact on common elements. For non-structural changes, a simple majority of owners representing a majority of participation quotas typically suffices. But structural walls or the building’s envelope? Many statutes demand a three-fifths majority—some communities have raised that to two-thirds. Check your community’s internal statutes; they may impose stricter thresholds than national law. Skip this step, and the community can issue a cease-and-desist order, halt your construction, and demand restoration at your own cost. By 2026, more communities have adopted internal rules requiring a refundable deposit or specific liability insurance for any works on shared areas—typically €500 to €2,500 per project, depending on scope and building age.

“Even if your municipal permit is approved, without community approval your works are illegal under civil law. The community can sue for restoration and damages, independent of any municipal sanction.”

This isn’t a theoretical warning. Courts routinely side with communities in these disputes. You could face dual penalties: a municipal fine for unauthorised works and a civil judgment to reverse the renovation. Always secure the community’s written acta before engaging any contractor.

Technical Compliance: The CTE, Energy Efficiency, and Final Certification

Subsection: Código Técnico de la Edificación (CTE) Requirements in 2026

Every renovation in Spain, no matter how small, must comply with the Código Técnico de la Edificación (CTE), the national building code covering structural safety, fire protection, accessibility, and energy efficiency. In 2026, the energy efficiency rules are stricter than ever. The updated Documento Básico de Ahorro de Energía (DB-HE) sets tough limits on thermal transmittance for facades, roofs, and floors. So, if you replace windows, you must install units with specific U-values—typically below 1.4 W/m²K for most climate zones. Touch an exterior wall, and you will likely need to add insulation to meet the new envelope standards. The rules also extend to heating and cooling: any new system must be high-efficiency, and in many cases, you will be required to integrate renewables like aerothermal or solar thermal, even if that was not in your original plan. Critically, the CTE follows a “renovation trigger” principle: modify one element, and you must bring it up to current code; sometimes, adjacent systems must be upgraded too. For instance, replacing a boiler could force you to improve the insulation on its pipework. Budget for these mandatory upgrades—they can add 15–25% to your projected costs.

Subsection: The Fin de Obra Certificate and Qualified Professional Sign-Off

Construction finishing does not end the legal process. A qualified professional—an architect or technical architect (aparejador)—must issue the certificado de fin de obra, a formal document confirming the executed works match the approved project and meet all CTE regulations. This certificate is mandatory. You must submit it to the ayuntamiento (city council) to legalize the renovation and update cadastral records. Without it, you cannot legally change the property’s characteristics, and selling or refinancing becomes difficult, as notaries and registrars will refuse to process the transaction.

To ensure compliance:

  • Hire a qualified professional to supervise the works (dirección de obra and, where required, coordinación de seguridad y salud). This is a legal duty, not a suggestion.
  • Submit the signed fin de obra certificate to the ayuntamiento within the stipulated period, usually one month after completion.
  • Be aware that some municipalities will conduct a final inspection before issuing a cédula de habitabilidad (occupancy certificate), which is required for residential rentals or sales.
  • Keep all permits, certificates, and technical reports indefinitely. You will need them for future renovations, refinancing, or selling. Losing these documents can trigger a costly, time-consuming legalization process.

Fines, Stop-Work Orders, and Legalization: What Happens If You Don’t Get a Permit

Municipal Sanctions and Penalties in 2026

Building without the required permit isn’t a minor oversight—it’s a direct breach of municipal planning law, and in 2026, town halls across Spain are cracking down harder than ever. The fine you face depends on where you are and, crucially, how serious the violation is. Minor infractions—like moving interior partitions, swapping out flooring with no structural impact, or adding a bathroom without touching load-bearing walls—typically draw fines between €600 and €3,000. Major structural changes are a different story. If you’ve altered load-bearing walls, expanded the building’s footprint, changed the roofline, or turned a terrace into a habitable room without a license, expect fines from €6,000 to €60,000 or more, depending on the works’ value and the city’s own rules. The financial hit isn’t the only consequence. The town hall can issue a decreto de paralización—an immediate stop-work order. That’s not a suggestion; it’s a binding legal directive that halts all site activity, often enforced with municipal inspectors and police present. Keep working after that order, and you’re facing a separate, more serious offence—one that can bring daily fines and even criminal charges for disobedience.

Legalization vs. Demolition: Your Options After an Infraction

Once you’re caught, you generally have two routes—and the decision isn’t entirely yours. The first is legalization. If the unauthorized work can be made to comply with current zoning and building codes—say, a new interior wall that meets fire safety and structural loading standards—you can submit a retroactive permit application. The town hall reviews it as if it were new, but with extra scrutiny because a violation already exists. If approved, you’ll pay the original license fee (usually 1% to 4% of the works’ value) plus a late-filing surcharge, often around 10% of that fee. But legalization isn’t guaranteed—it’s at the town hall’s discretion. If the work can’t be legalized, demolition follows. That happens when construction breaches setback rules, exceeds height limits, encroaches on protected heritage zones, or conflicts with the General Urban Plan. In those cases, the town hall orders demolition at your expense—and you still owe the fines. In 2026, many municipalities are using satellite imagery and inspection drones to spot illegal renovations, especially in coastal areas and historic centres, so getting caught is more likely than ever.

“Legalization is not a right—it’s a discretionary decision by the town hall. If the works are in a protected area or violate the General Plan, demolition is the likely outcome, and you will pay for both the demolition and the fines.”

Practical Tips for a Smooth Permit Process in 2026

The single most effective way to avoid delays, fines, or a halted obra is to bring a local professional into your corner before you buy a single tile. Spain’s renovation rules are not uniform; each autonomous community shapes them, and your specific municipality’s Plan General de Ordenación Urbana (PGOU) matters most. A local architect or technical architect (aparejador) knows this patchwork intimately. They can quickly determine whether your project needs a full licencia de obras mayor, a streamlined licencia menor—for small, non-structural changes like a kitchen or bathroom update—or merely a declaración responsable, a sworn statement that your works comply with regulations, letting you start immediately in many cases. Self-diagnosing your permit category is a gamble; misclassification is a top trigger for stop-work orders and retroactive fines in 2026.

Your architect will also handle the technical documentation, which has grown stricter this year. Since the 2024 reform of the Código Técnico de la Edificación (CTE), even minor renovations often require a Libro del Edificio update and, for any work touching energy efficiency, a certified thermal envelope calculation. A local professional knows precisely which annexes your ayuntamiento expects—from geotechnical studies to waste management plans, mandatory for any demolition, even partial. They’ll also guide you through current digital submission portals. Most major cities now require online filing with a digital signature, and the interface varies wildly from Valencia to Seville.

Budget for their fees realistically. For a single apartment renovation, expect €1,200 to €3,500 per project for a full permit package, covering drawings, technical specs, and submission. If you only need a declaración responsable, a technical architect’s fee typically runs €400 to €900 per project. This isn’t where you cut corners. Correcting a rejected application—or worse, legalizing unpermitted work after a neighbor’s complaint—will easily triple that amount. A local professional also maintains working relationships with municipal planners, which can mean the difference between a three-week approval and three months of bureaucratic silence. In 2026, the rule is simple: pay for expertise upfront, or pay for penalties later.

Frequently asked questions

Do I always need a building permit for a renovation in Spain in 2026?
No, but the threshold is strict and varies by autonomous community. Since the 2024 state-level harmonization update, minor works like repainting or replacing flooring typically require only a ‘comunicación previa’ (prior notice), while any structural change, layout modification, or alteration to the building’s exterior almost always requires a full ’licencia de obras’. Check your local town hall’s urban planning department, as municipal ordinances can impose stricter rules than regional ones.
What is the difference between a 'licencia de obras mayor' and a 'licencia de obras menor' in 2026?
A ’licencia de obras mayor’ is required for renovations that affect the structure, load-bearing walls, facades, roof, or total surface area, and it involves a full architectural project and technical review. A ’licencia de obras menor’ applies to small, non-structural works like interior partitions, bathroom updates, or window replacement, and it is processed faster with a simplified application. Since 2026, many municipalities have digitized these processes, but the classification remains based on the technical complexity and risk of the work.
Can I start renovation work while my permit application is pending in 2026?
Generally, no. Starting work before receiving the final permit is a serious infraction, leading to fines, work stoppage orders, and even demolition orders for illegal changes. However, some regions now allow a ‘declaración responsable’ (responsible declaration) for minor works, which lets you start immediately after filing, but only if your project qualifies as ‘minor’ under the 2026 updated regulations. For major works, you must wait for explicit approval; no implicit approval (silencio administrativo) is accepted for starting construction.
What documents do I need to submit for a renovation permit in Spain in 2026?
The standard package includes the DNI/NIE of the owner, the cadastral reference and property title (escritura), a technical description of the works, and, for major works, a project signed by a qualified architect and a technical architect (aparejador). Since 2026, most town halls also require an energy efficiency certificate for renovations affecting insulation or HVAC systems, and a waste management plan. If the building is listed or in a protected area, you must add a heritage impact report from the regional culture department.
How long does it take to get a renovation permit in Spain in 2026?
For minor works, the average response time is now 1 to 2 months, thanks to mandatory digital processing in most municipalities. For major works, expect 3 to 6 months, but this can extend to 12 months if your project requires heritage or environmental reviews. If the town hall does not respond within the legal deadline (typically 2 months for minor, 3 for major), you can file a ‘silencio administrativo’ request, but note that for major works, silence is often negative, meaning your application is denied by default.
Are there any new digital requirements for permits in 2026?
Yes, since January 2026, all Spanish municipalities with over 20,000 inhabitants must accept permit applications exclusively through their electronic headquarters (sede electrónica), using a digital certificate or Cl@ve system. You must submit all plans in a machine-readable format (e.g., PDF/A with vector layers), and some cities now require BIM (Building Information Modeling) files for complex renovations. For small towns, paper submissions are still allowed, but they are increasingly discouraged in favor of the national ‘Plataforma de Trámites Urbanísticos’.
What happens if I renovate without a permit in Spain in 2026?
Penalties have been significantly increased in 2026: fines range from 300 to 6,000 euros for minor infractions, and from 6,000 to 120,000 euros for major ones, depending on the damage to urban planning regulations. You will also face a mandatory ’legalización’ process, where you must hire an architect to certify that the works comply with current codes, or face demolition if they don’t. Additionally, the town hall can prohibit you from selling or renting the property until the situation is resolved, and the statute of limitations for illegal works is now 8 years, but it resets if you hide the work.
Do I need a separate license for plumbing, electrical, or HVAC work in a renovation?
In 2026, you do not need a separate building permit for these trades, but they must be included in the main permit application, and each licensed professional (electrician, plumber) must submit their own ‘boletín’ (certificate of installation) after completion. For simple replacements (e.g., changing a water heater), a ‘comunicación previa’ to the local industry department is sufficient, but for full rewiring or new HVAC systems, you must provide a project annex signed by a competent technician. The final ‘certificado de fin de obra’ must list all these installations for the occupancy license.
How do heritage protection rules affect renovation permits in 2026?
If your property is in a ‘Bien de Interés Cultural’ (BIC) zone or a listed building, you need explicit approval from the regional heritage authority before the town hall can issue a building permit. In 2026, this approval is mandatory for any work affecting the facade, roof, or structural elements, even if the work is minor; interior changes that don’t alter the protected character may only need a notification. The process adds 2 to 4 months to your timeline, and you must use traditional materials and techniques unless you obtain a special exception, which is rarely granted.
What is the 'licencia de primera ocupación' and do I need it after a renovation?
The ’licencia de primera ocupación’ (first occupancy license) is required if your renovation changes the number of dwellings, the usable surface area, or the building’s use (e.g., converting a garage into a studio). For renovations that don’t alter the layout or use, you only need a ‘certificado de fin de obra’ signed by the architect and approved by the town hall. Since 2026, this certificate must include a georeferenced plan and a declaration of compliance with the current Technical Building Code (CTE), and you must submit it within 3 months of completing the works.